The project is estimated to cost $165 million. Detailed cost estimates by expenditure category and by financier are included in the project administration manual.

 

Summary of Cost Estimates (Revised)

(US$ million)

 

Item

 

Amount

Based Cost

 

Innovative technology learning and research environment established

 

Quality and industry-relevant higher technology education programs implemented

 

Industry linkages and international collaborations strengthened

 

Faculty management capacity strengthened

 

New higher education project preparation supported

 

Financial Charges During Implementationd

 

 Total Loan

 

 

Project Management Expenses, Taxes & Duty

 

 

 

 

 

 

120.372

 

02.408 

 

06.320

 

0.200

 

0.400

 

15.300

 

145.00 

 

 

20.00

 

165.00

 

 

The implementation arrangements are summarized in this table and described in detail in the project administration manual. 

 

   Aspects

 

 

Arrangements

 

 

 

  Implementation period

 

  Estimated completion date

 

   Revised Completion date

 

  Estimated loan closing date

 

  Revised loan closing date

 

  Management

 

 

    -Oversight body

 

 

 

 

 

    -Executing agency

 

 

    -Key implementing  agencies

 

 

 

 

 

 

 

 

September 2018- December 2023

 

31 December 2023

 

31 December 2024

 

30 June 2024

 

 30 June - 2025

 

 

 

Project steering committee secretary, MHECA (chair)

Four vice chancellors, UGC, and other agencies (members)

 

 

MHECA

 

 

Universities of Kelaniya, Rajarata, Sabaragamuwa, and Sri Jayewardenepura